Charlotte Airport Pitches Gates and Tunnel
Charlotte Douglas International Airport (CLT) wants to add gates to Concourse C and dig a passenger tunnel linking it to the main terminal.
The gates and tunnel anchor a package of nearly a dozen projects, called CLT Beyond, that the airport is folding into its new lease with American, Delta, Frontier, Southwest, and United. The airport hasn’t said what it all costs, and city council will hear the pitch Monday before voting at a later meeting.
Also in the mix: a renovated international arrivals area, electrical upgrades, and airfield work to prepare for the $1 billion fourth parallel runway, a 10,000-foot strip due to open in fall 2027.
CLT’s last big terminal job, the $241 million Concourse A expansion, opened in September 2024 with 10 new gates. Work on Concourses D and E is still underway. |