NCDOT Plans $342.5M U.S. 64 WideningThe North Carolina Department of Transportation will hold a public meeting Nov. 18 on its $342.5 million plan to widen U.S. 64 through Apex and Cary. Plans call for widening the highway to six lanes from just west of Laura Duncan Road in Apex to U.S. 1 in Cary. New interchanges at Laura Duncan Road and Lake Pine Drive would carry both roads over U.S. 64. Traffic already runs from more than 40,000 vehicles a day near Laura Duncan Road to over 56,000 at U.S. 1, and NCDOT expects volumes to climb more than 40% by 2040. Before any widening, NCDOT will extend the CSX railroad bridge west of Laura Duncan Road under a separate contract, with that work expected to begin in 2028. Construction on U.S. 64 itself isn’t expected until 2031. The drop-in meeting runs from 5 to 8 p.m. at the John M. Brown Community Center, 53 Hunter St., in Apex. The public can comment through Dec. 18. |
|
|